Energiewende: a turning point ahead?

With an estimated cost of EUR520 billion by 2025, electricity bills for average households more than doubling by the same date, utilities facing huge impairments, the electricity system losing reliability, and with rather poor results obtained in terms of environmental targets originally set, the German Energy Transition process (Energiewende) may well be deemed a complete fiasco.

In 2011, Germany’s decision to shut down its nuclear power plants fleet became an element of distortion for the already ongoing Energiewende (Energy Transition) process. Here we shall look into the nuclear phase-out development, as well as into its most important consequences, and which have negatively impacted the goals initially set by the Energiewende.

By the end of 2010, the country´s 17 nuclear power reactors accounted for approx.15% of the total installed capacity (20,48GW) and supplied 133TWh, more than 25% of the electricity consumed, with legislation at the time requiring their shut down by 2036. However, in the aftermath of Fukushima´s nuclear disaster in 2011, the German government decided to almost immediately shut down 8 of its nuclear power reactors (8,41GW), and phase out the remaining 9 units by 2022 (one of which, Grafenrheinfeld, 1,27GW, was closed in 2015).

According to latest data published by the BNetzA (Bundesnetzagentur), the Federal Network Agency, the proposed shutdown calendar for the remaining units looks as follows:

As can be observed, and if we assume that Gundremmingen (1,284GW) is taken off the grid by the end of this year, a total 9,516GW will be phased out between 2019 and 2022 if everything goes according to plan.

Very high costs for end-users:

In order to make up for this ‘self-imposed’ reduction in installed capacity, an impressive roll-out of renewable energy resources has been taking place, namely wind and solar technologies, the latter by means of heavy subsidies which have proven unsustainable in the long run, and are partially to blame for the significant increase in power prices borne by end-users. A complete contradiction, one might think, given that one of the main targets of the EU Power Market Liberalization Directive and, in turn, of the Energiewende, is to significantly reduce the electricity bills of households.

The table below provides us with a very well-defined picture of cost distribution and evolution of average power prices over the last 10 years for households using 3.500 kWh/yr.

Note: updated to February 2017

As we can see, the cost inherent to renewable surcharges increases significantly from 2013 onwards, and becomes one of the main reason why prices to end-users have experienced a rise of approx.12.6% (3,27cts/kWh) since 2012.

Note: the need to expand the transmission network (please see further below) is also affecting end-users´ bills. In the above graph, we can observe that ‘Grid fee’ associated costs have seen a considerable increase since 2013, a component which is only bound to rise in years to come.

 

Loss of power supply reliability

However, relying on renewable power generation to partially compensate for the country´s nuclear phase-out, is faced with two main obstacles: 1) the intermittent nature of renewable power technologies and, 2) the difficulties encountered to transport off-shore wind power, the most reliable and efficient kind of renewable power generation, and located in the northern part of the country, to the South, which is scarcely interconnected with the rest of the country and relies heavily on imports from Switzerland.

It is for these reasons that Germany has put in place a series of “Reserve Systems” to ensure security of power supply:

  1. In July 2015, after months of intense negotiations, the government scrapped its proposed levy on coal-fired plants and resolved that, as part of a revised capacity mechanism regime, approx. 2.7GW of lignite-powered generating capacity (representing about 13% of installed lignite power) would be gradually transferred to a ‘Security Standby Reserve‘ (Sicherungsbereitschaft), and which is completely independent from any other ‘Reserve System’. Such transfer would take place between 2016 and 2020 by negotiations with RWE (1.45GW), Vattenfall (0.93GW) and Mibrag (0.35GW). This capacity would be brought online when needed and then progressively shut down after four years. The three utilities would receive €230 million per year compensation over seven years, total €1.6 billion. The EC approved the arrangements in May 2016 under state aid rules. In fact, rather than a ‘Reserve System’, this seems to be more of a kind of ‘arrangement’ to compensate utilities for the coal phase-out process, this last one being another goal set by the Energiewende.
  1. Unlike countries such as the U.K. and France, which have introduced the so called ‘Capacity Mechanism market’ to ensure long-term security of supply, Germany has chosen to introduce a safety mechanism which uses a ‘Capacity Reserve’ to be built from 2017 onwards, and will reach its target value of 5% of the German annual peak load (approx. 4.4GW) from 2019 onwards. This reserve is procured competitively by means of necessary calls for tenders. The power plants conforming the capacity reserve are fully kept outside the electricity market in order not to influence it, nor may they return to the electricity market (“no-way back rule”). The procedures for procurement and use are regulated in detail in a newly created capacity reserve system.
  1. Finally, there is also the ‘Reserve for the Stabilization of the Transmission Network’ in Southern Germany, which has so far been used above all in extreme weather events such as strong winds. This reserve is to be supplemented by a maximum of 2 GW of new network reserve installations in Southern Germany which are also to be contracted within the framework of a competitive procurement procedure. This new construction network capacity is calculated on the quantity of capacity reserve to be announced. The exact tender conditions for the new construction network reserve are specified this year on the basis of an analysis of the transmission system operators. A certain interlocking of the capacity reserve and the grid reserve is to be made possible by the fact that installations of the grid reserve (with the exception of new-built assets which receive a 15-year-old fixed remuneration) are also entitled to the capacity reserve and can switch to this in the case of success.

The table below shows total capacity committed to a ‘Reserve Status’ as per BNetzA (Federal Networks Agency) data of March 31st, 2017.

Primary energy consumption and greenhouse gas emissions reduction targets at risk

The need to use a considerable amount of electricity production originating from both coal and gas-fired based power plants (existing and new-built) in order to guarantee the stability of the electricity system is compromising Energiewende´s environmental targets:

  • Reduction of Primary energy consumption (compared to 2008): -20% by 2020.

However, according to BNetzA´s Monitoring Report 2016, the target achieved in 2014 was -8.3% (1.6%/yr 2008-2014), whereas 2015 showed an even lower value, -7.6% (1.3%/yr 2008-2015). Hence, reaching the -20% target by 2020 seems to be completely out of the picture.

  • Reduction of greenhouse gas emissions (compared to 1990): -40% by 2020.

According to think tank Agora Energiewende, emissions saw a total reduction of approx. 28% in 2016, and their most realistic forecasts place them at 30-31% by 2020, rather than the overestimated 35% recently announced by the German government.

Major utilities facing huge impairments

Obviously, the decision to dismantle Germany´s nuclear power fleet did not come without controversy, with affected utilities pressing claims for compensation on the basis of continuing with the nuclear tax linked to license extensions agreed in September 2010, write-down of plants, cancelled upgrades which were already ongoing at the time, and also decommissioning costs brought forward. With the total amount of claims adding up to a few billion Euros, the Constitutional Court of Karlsruhe has given the right to the operators of the plants, leaving these and the government to agree on a final figure before spring 2018.

In this context, we should mention that a dispute concerning the management of radioactive waste was resolved in December 2016, with nuclear utilities having to pay EUR23.6 billion into an energy phase-out fund no later than 2026, and being then cleared of any liability for final disposal of used fuel. The deal will leave German taxpayers footing a potentially sizeable proportion of the bill, especially for the disposal of nuclear waste in the long term. The German Institute for Economic Research in Berlin (DIW) estimates that the nuclear phase-out, which, including clean-up operations, will take at least several decades, could reach 170 billion euros.

CONCLUSION

Germany´s decision to unilaterally phase out its nuclear power fleet by 2022 means that a rather considerable amount of electricity production generated by intermittent renewable assets will need to be backed up by fossil fuel based power plants in order to guarantee the stability of the electricity system.

One of the most immediate implications is that the Energiewende is resulting incredibly expensive. The following table shows an indication of detailed actual and forecasts costs:

These huge costs result in end-users seeing their electricity bills rise considerably, by an estimate of approx. EUR20.00/month by 2025 (calculations based on the consumption of an average 4-person household).

But, equally important, the country´s Energy Transition project, at a time viewed by other countries as a model to follow, is failing to reach some of its most important environmental targets in the short-term (2020).

It is now obvious that the Energiewende´s initial approach was far too ambitious. But, most importantly, where is it heading to right now? Or, put into other words, should it take a few steps back before becoming just the piece of paper it is written on?

Suscribe to our Newsletter

Each month, one of our experts publishes an article describing his view on a specific topic of the constant changes taking place in the energy market, with special focus on the French market.

Profesional Experience & Education

Diego graduated in Political Economy at King’s College University (London – 2021). He started his professional career in a family business in Madrid as an operations manager. Diego then studied a Master in Management and Master in Computer Science at IE University (Madrid – 2022), during which he participated as an Information Technology (IT) intern in a startup. In May 2023, Diego joined the HES team as an intern specialised in programming models. In his first project, he developed a software tool for modelling the unavailability of the French nuclear fleet. Afterwards, Diego has also participated in the development of new software tools for modelling price curves, generation asset performance and other topics related to the energy market. 

Diego Marroquin

Junior Consultant

Haya Energy-6

Profesional Experience

Céline joined Haya Energy Solutions in November 2021 as marketing and administration manager. She had a first professional experience in the tourism sector as a social media manager. At HES, her activities are focused on the development of the company’s visibility at European level through: commercial actions, content marketing and development of brand strategy. Céline is also involved in the management of the company’s communication: optimisation of the website (WordPress & Elementor), LinkedIn, publication of the monthly newsletter and the organisation of conferences. Céline participates in energy projects with the clients and acts as coordinator and project manager. Finally, she is in charge of administration (accounting, expenses management, invoicing).   

Education

Céline graduated in Spanish and English Philology at La Sorbonne (France – 2018) and holds a Master’s degree in Project Management and Cultural Tourism (Clermont-Ferrand/ Buenos Aires – 2021). 

Céline Haya Sauvage

Marketing Responsible

Céline Sauvage

Investment Advice

“Decarbonization of the Energy and Transport sectors is arguably today’s main economic driver for the industry.”

Profesional Experience

His career started in civil engineering as a Project Manager in France, Martinique and Australia. Afterwards, he became the General Manager of a subsidiary in Venezuela. In 1992, he established Dalkia in Germany (district heating, cogeneration, and partnerships) and represented Véolia in Thailand. In 2000, he opened the commercial office of Endesa in France to take advantage of the liberalized retail market. From 2006, as a development Manager at Endesa France, he led Endesa’s plan for Combined Cycle generation in France and developed the wind and PV portfolio of Snet at the same time. Philippe Boulanger worked for 3 years at E.ON’s headquarters coordinating the company´s activities in France. He was strongly involved in the French hydro concession renewal project. As a Senior Vice President – Project Director at Solvay Energy Services from April 2012 to February 2014 he was in charge of the H2/Power to gas and European direct market access deployment projects. Philippe has been an HES expert since 2014.

Education

Philippe Boulanger holds engineering degrees both from the Ecole Polytechnique and the Ecole Nationale des Ponts & Chaussées (France) and has a combined experience of more than 25 years in energy and infrastructure. In addition to English, Mr. Boulanger is fluent in French, German & Spanish.

Philippe Boulanger

Electricity Expert

HES-Philippe-Boulanger

“The world is changing. New investors pay particular attention to the energy sector while historical actors adapt their position to the market.”

Profesional Experience

Antonio started his career in the electricity sector in 1991 working as a member of the General Manager’s team at Sevillana de Electricidad (Spain). In 1997, he was appointed head of commercial regulation at Endesa Distribución. In 2000, he joined the mergers and acquisitions (M&A) department of Endesa Europe. He was appointed Managing Director of Endesa Power Trading Ltd (UK) in 2003. A year later, he became responsible for energy management at SNET (France). In 2008, he was appointed Managing Director of SNET (France). In 2009, he became Director of Corporate Development at E.ON France. In 2011, he founded Haya Energy Solutions (HES), a consulting firm focused on optimising the energy management of consumers, producers and retailers of gas and electricity. From 2015 to 2018, Antonio combined the consulting activity at HES with the general management of 2 production facilities in France (2 CCGTs x 410MW), owned by KKR. At the end of 2018, he joined Asterion Industrial Partners, an infrastructure investment fund, as an operating partner. Antonio currently devotes most of his efforts to the Asterion Portfolio, while advising through HES companies in the energy sector in France, Italy, Germany, UK and Spain. 

Education

Antonio graduated from the Escuela Técnica Superior de Ingenieros of Seville (Spain) and holds an MBA degree from Deusto University (Spain). 

Antonio Haya

CEO